Project: Impact Assessment Guidance and Support

Reference: R215

Last update: 15/08/2013 11:44:31

Objectives

The objectives of this project are to:

a) Deliver DfT Policy focused guidance on impact assessments

b) incorporate guidance on impact assessments into WebTAG as part of the NATA Refresh work-programme

c) provide call-off consultancy support for policy divisions to help them produce impact assessments

Description

The project will apply research undertaken by the Department and external groups to the impact assessments for regulation and policy options being considered by the Department in its decision making process.

Contractor(s)

WSP Ltd
66-68 Hills Road, Cambridge, CB2 1LA

Contract details

Cost to the Department: £18,847.50

Actual start date: 21 August 2007

Expected completion date: 30 March 2010