Project: Assessment of the Economic and Social Impacts of Clear Zones

Reference: UG335B

Last update: 20/11/2003 16:00:48

Objectives

The objective of this project is to establish a common assessment framework to assess the social and economic impacts of Clear Zones.

Description

This project intends to define suitable methods for the assessment of the economic and social impacts of a Clear Zone. This is to be published in a report for use by authorities implementing Clear Zones. The report is to:

1. recommend methods of assessing the economic and social impacts on Clear Zones;
2. assess data issues, such as availability and reliability;
3. illustrate impact of results via a case study of Winchester.

Contractor(s)

CAG Consultants
Gordon House, 6 Lissenden Gardens, London, NW5 1LX
020 7482 8882

Contract details

Cost to the Department: £49,301.28

Actual start date: 30 October 2001

Actual completion date: 01 December 2002

Publication(s)

Clear Zone reports
Author: Various
More information: http://www.dft.gov.uk/pgr/roads/tpm/clearzones/clearzonespublications/

Summary of results

  1. http://www.dft.gov.uk/clearzones

Departmental Assessment Status: Project completed prior to the implementation of the Departmental publications scheme.