Project: MOT Testing of Cars with Control Adaptations

Reference: 305FDM

Last update: 19/11/2003 15:19:29

Objectives

The objective of this project is to gather facts on the costings, technical problems, legislation issues and options on which to consider policy issues on testing.

Description

This project intends to deliver a report on the costings and feasibility of including in MOT tests, the following:

1. an inspection of control adaptions;

2. and inspections of cars with newly fitted control adaptions.

Contractor(s)

TRL Limited
Crowthorne House, Nine Mile Ride, Wokingham, Berkshire, RG40 3GA
+44 (0)1344 773131

Contract details

Cost to the Department: £92,765.96

Actual start date: 29 April 1992

Actual completion date: 31 March 2005

Publication(s)

TRL reports PR/SE/086/00 AND PR/SE/264/01
Author: TRL
Publication date: 01/01/2001