Review of system for making orders - Final Report
Table of contents
- Front cover
- Document Control
- Summary
- Introduction
- Extent of Powers Within the Act
- The One-Stop Shop: Consents Under Other Enactments
- Pre-Application
- The TWA Application
- Parliamentary Scrutiny
- Pre-Inquiry
- Inquiry/Alternative Procedures
- Decisions and Post-Decisions
- DTLR Resourcing and Processing
- Good Practice Guidance and Training
- 1 Introduction
- 1.1 Appointment
- 1.2 Objectives
- 1.3 Our Approach
- 1.4 This Document
- 2 Experience of TWA orders to date
- 2.1 Summary of Applications
- 2.2 Average and Range of Times from Application to Decision
- Table 2.1 Average Times for Processes (in months)
- Table 2.2 Range of Times for Processes (in months)
- 2.3 Analysis and Key Component
- 2.4 Processing by TWA Unit
- Table 2.3 TWA Unit Targets and Achieved Times (in months)
- 2.5 Issues Arising from Draft Orders
- 2.6 Changes in Government Regulations or Guidance
- 2.7 Outstanding Issues from Inspector's Report
- 2.8 Correspondence during Decision Stage
- 2.9 Delays in DTLR Receiving Replies
- 2.10 Related Applications
- 3 Research into relevant documents
- 3.1 Introduction
- 3.2 Current TWA Statutes and Guidance
- 3.3 Other Government Regulation and Guidance
- 3.4 Relevant Government Discussion Papers and Statements
- 3.5 Reports from Industry Bodies and Environmental Organisations
- 4 Consultation responses
- 4.1 Form of Consultation
- 4.2 Issues from the Questionnaire Survey and Seminar - General Pre-Application
- 4.3 Issues from the Questionnaire Survey and Seminar - Powers and Procedures.
- 4.4 Development Workshops
- 4.5 Survey of Individual Objectors
- 5 The scope and powers of TWA
- 5.1 The Nature of the TWA
- 5.2 Works covered by the TWA
- 5.3 Extension of powers under the TWA
- 5.4 Delegation of TWA decisions
- 6 The TWA process as a one stop shop: consents under other enactments
- 6.1 General
- 6.2 Consents under the Railways Act 1993
- 6.3 Listed Building and Conservation Area Consents
- 6.4 Traffic Regulation Measures Under the Road Traffic Regulation Act 1984
- 6.5 Other Consents
- 7 Pre-application
- 7.1 Introduction
- 7.2 The Role of Development Plans in Facilitating the Growth of the
- 7.3 Consultation Procedures
- 7.4 Consultation Procedures - Environmental Assessment
- 7.5 Vetting of Schemes
- 7.6 The Involvement of Concessionaires/Contractors
- 8 The TWA application
- 8.1 The Draft TWA Order: Model Clauses
- 8.2 Model Clauses for Utilities
- 8.3 Application Requirements
- 8.4 Additional information to be submitted with the Application
- 8.5 Fast tracking and flexibility
- 9 Parliamentary scrutiny
- 9.1 Introduction
- 9.2 Benefits of a Parliamentary Process
- 9.3 Objections raised to a parliamentary process
- 9.4 Limitations of section 9 parliamentary procedure
- 9.5 Further Considerations
- 9.6 Conclusions
- 10 Pre-inquiry
- 10.1 Introduction
- 10.2 Pre-Inquiry Negotiation/Mediation
- 10.3 HMRI Input
- 11 Inquiry/alternative procedures
- 11.1 Inquiry Procedures and conduct
- 11.2 Planning Inquiry Procedures
- 11.3 Transport and Works Act Inquiry Procedures
- 11.4 Use of Appropriate IT
- 11.5 Late objections
- 11.6 Power to amend TWA Application Documents
- 11.7 Amendments to Environmental Statements
- 11.8 Written representation procedures, informal hearings and the use of mediation
- 11.9 Delays at Decision Stage
- 12 Decisions and post-decisions
- 12.1 Shortening the Decision Stage
- 12.2 Statutory challenge/judicial review
- 12.3 Extension of time for existing Orders
- 12.4 Delays Due to Need for Correspondence During the Decision Stage
- 13 DTLR resourcing and processing
- 13.1 Introduction
- 13.2 Resourcing
- 13.3 Processing
- 13.4 Conclusions
- 14 Good practice guidance and training
- 14.1 Documentation
- 14.2 Training
- 15 Links with proposals under the modernising planning agenda
- 15.1 Introduction
- 15.2 References to Consultation Documents
- 16 Next steps
- 16.1 General

