WORK TO REMOVE STERN OF MSC NAPOLI TO START IN MAY

Work to remove the remaining section of MSC Napoli from Lyme Bay will begin in early May 2008. The remaining part of the stern section of the vessel remains aground in Lyme Bay with a list of 40 to starboard.


Stern section of the MSC Napoli

Shaped explosives will be used to remove the propeller, the rudder, and to cut the propeller shaft. They will also be used to weaken the structure of the main engine to assist its removal. The aft section will then be systematically removed. The whole operation is expected to take roughly five months. SOSREP (Secretary of States Representative for Maritime Salvage and Intervention) has made the decision to cut up the remaining section and take it away in small pieces, rather than removing it in larger pieces, following analysis of all options available. The option to cut the remaining section into smaller pieces is preferable since there could be issues with anchoring and cutting through the main engine and propeller shafting if the stern were cut up into larger pieces.

A pollution control plan will be in place throughout the entire operation. Following removal from the site, material will be transhipped to Holland for recycling. On completion a full underwater survey will be carried out to ensure that the seabed has been cleared of all recoverable debris from the MSC Napoli.

Throughout the winter, weather permitting, contractors have been conducting an inspection of the wreck, in daylight, on a fortnightly basis. When on site they have been checking for any change in status of the wreck and any evidence of pollution. They have also been recording photographs showing the status of the wreck. Inspections have been co-ordinated with periodical aerial inspections which have been carried out by MCA surveillance aircraft.

The Napolis owners also have a response team from DRS, based in Branscombe, who have been monitoring the wreck and the Branscombe area daily. They have been patrolling and clearing any material which may have originated from MSC Napoli from all beaches in the Lyme Bay area.

Despite periods of severe weather over the last few weeks there is still no change in the status of the wreck.